CNOOC Ltd. has brought onstream its Suizhong 36-1/Luda 5-2 project in the shallow waters of the Bohai Sea, the company said Feb. 5.
CNOOC’s operated Suizhong 36-1/Luda 5-2 oilfield secondary adjustment and development project is in water depths of about 30 m in Bohai Sea’s Liaodong Bay.
The main production facilities include two new central processing platforms and two new wellhead platforms. CNOOC plans 118 development wells, including 81 producers and 37 water injection wells. The project is expected to reach peak production of approximately 30,300 bbl/d in 2025.
CNOOC said this project represents the largest secondary development and adjustment project offshore China. The development relies on onshore power supply.
CNOOC Ltd. holds 100% interest in the project.
Recommended Reading
EQT Declares Quarterly Dividend
2024-04-18 - EQT Corp.’s dividend is payable June 1 to shareholders of record by May 8.
E&P Earnings Season Proves Up Stronger Efficiencies, Profits
2024-04-04 - The 2024 outlook for E&Ps largely surprises to the upside with conservative budgets and steady volumes.
Analyst Questions Kimmeridge’s Character, Ben Dell Responds
2024-05-02 - The analyst said that “they don’t seem to be particularly good actors.” Ben Dell, Kimmeridge Energy Partners managing partner, told Hart Energy that “our reputation is unparalleled.”
Sunoco’s $7B Acquisition of NuStar Evades Further FTC Scrutiny
2024-04-09 - The waiting period under the Hart-Scott-Rodino Antitrust Improvements Act for Sunoco’s pending acquisition of NuStar Energy has expired, bringing the deal one step closer to completion.
Kimmeridge Fast Forwards on SilverBow with Takeover Bid
2024-03-13 - Investment firm Kimmeridge Energy Management, which first asked for additional SilverBow Resources board seats, has followed up with a buyout offer. A deal would make a nearly 1 Bcfe/d Eagle Ford pureplay.